Contract programme
Constructing a building is a complex process which involves the co-ordination of many multifaceted resources. To ensure the project achieves the requisite time and budgetary constraints, detailed programmes are devised to eliminate.
There are several areas of work that require detailed planning, one of which is the contract programme. Typically, the successful contractor will start planning the project in great detail as soon as they have signed the construction contract. It is usually the contractor’s responsibility to specify the order in which the work will be undertaken. This will require a close examination of what resources are available, assessing the time that may be required and the impact that subcontractors, suppliers and other third parties will have on the programme.
Using the information in the contract documents, the contractor usually prepares a method statement in the form of a schedule that divides the intended construction work into operations; this will encompass the labour and plant requirements – and their availability – associated with each work element. This information is then converted into a draft programme and circulated to all management personnel associated with the project. Once they have had enough time to consider the proposals, they can discuss the contents so that working methods and amendments can be agreed.
Time overruns are common in construction projects and contractors will try to avoid this happening by ensuring the work is completed earlier than the target completion date. This will be particularly pertinent if the contract involves the imposition of liquidated and ascertained damages after the agreed completion date.
The nature of the construction process means that a planned programme can also become unrealistic due to factors beyond the contractor’s control, such as inclement weather, materials delivered later than agreed, the client or designers giving late instructions and so on. If such circumstances occur, the contract programme should be updated to reflect the situation and include a revised action plan.
The co-ordination of material and component deliveries, subcontractor and trade work can be portrayed in visual representations based on the critical path method (CPM) and produced by complex software programmes. The CPM can provide an accurate reflection of site operations and the interrelationships between activities.
For more information see: Critical path and Programme for building design and construction.
Some forms of construction contract will require the prepartion of a programme by the contractor. For example NEC requires that the contractor prepares a programme for the works which is then submitted to the project manager for their approval. If it is approved, this becomes the 'accepted programme'. The programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resource they intend to use.
For more information see: Accepted programme.
Other forms of contract may require that the contractor provides a master programme for the construction of the works as soon as possible after the execution of the contract, if it has not been previously provided. However, as it is produced after the execution of the contract, the programme does not impose any obligation on the contractor beyond those obligations imposed by the contract documents.
For more information see: Contractor's master programme.
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Construction progress report.
- Construction stage report.
- Contractor.
- Contract administrator.
- Contractor's master programme.
- Critical path method CPM.
- Earned value analysis.
- Gantt chart
- How progress is agreed in construction.
- Long lead-time item
- Programme consultant.
- Project programme.
- Progress of construction works.
- Scheduling construction activities
.
Featured articles and news
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.


























